10th of June 2015

1. As non-Interconnected Islands Network Operator, following the Announcement dated on 5.6.2015 referring to the management of pending requests within the framework of the Special Programme for photovoltaic systems installation (PVs) on roofs, HEDNO informs the interested parties about the following Tables with the pending requests per electricity system:

Table of pending Requests of the Special Programme for PVs in Crete
Table of pending Requests of the Special Programme for PVs in Ikaria
• Table of pending Requests of the Special Programme for PVs in Karpathos
• Table of pending Requests of the Special Programme for PVs in Kythnos
• Table of pending Requests of the Special Programme for PVs in Astypalaia

Possible reconfirmation of the equivalent interest must be expressed within one (1) month from the issuance of the relevant letter (with delivery receipt) that will be sent to each interested party, otherwise the relative requests will be put into the archives.

2. As non-Interconnected Islands Network Operator, following the Announcement dated on 5.6.2015 referring to the automatic termination of the Offers of Connection with the Network for those that are exempted from acquiring RES plants permit for which the effective duration of the connection offer has passed inactive, HEDNO informs the interested parties about the Tables with PV Plants that are included in this category per electricity system:

• Table of PVs with automatic termination of the Connection Offer in Crete (Agios Nikolaos)
Table of PVs with automatic termination of the Connection Offer in Crete (Heraklion)
Table of PVs with automatic termination of the Connection Offer in Crete (Rethymno)
Table of PVs with automatic termination of the Connection Offer in Crete (Chania)
• Table of PVs with automatic termination of the Connection Offer in Rhodes
• Table of PVs with automatic termination of the Connection Offer in Mykonos
• Table of PVs with automatic termination of the Connection Offer in Lesvos
• Table of PVs with automatic termination of the Connection Offer in Milos
• Table of PVs with automatic termination of the Connection Offer in Karpathos
• Table of PVs with automatic termination of the Connection Offer in Limnos
Table of PVs with automatic termination of the Connection Offer in Kos-Kalymnos
• Table of PVs with automatic termination of the Connection Offer in Skyros
• Table of PVs with automatic termination of the Connection Offer in Chios
• Table of PVs with automatic termination of the Connection Offer in Syros

HEDNO will consider the above mentioned Connection offers as automatically terminated and will put the relevant requests to the archives with release of the capacity reservation in the Network, if the above mentioned contracting parties will not submit complete folder for readiness in the activation of their station within one (1) month from the issuance of the relevant letter (with delivery receipt) that will be sent to them.