For the rearrangement of the supply - meter, the relevant application form is submitted by the interested party to any service point. The consent of the property owner is necessary with the relevant Sworn Statement of L. 1599/86.

In order to proceed to the construction of the project, the following are required:

1.     Payment of a fee related to the supply-meter rearrangement expenses 

2.     Submission of the Licensed Electrician Certification/electrician certificate.

 For more information, please contact the competent service point.