Installation of auxiliary station with Generating Sets
Here you will find the applicable legislation and the documents required for the connection and operation of standby generating stations for the purpose of back-up supply.
Flowchart of the Connection Procedures for an auxiliary station with Generating Sets:
Legal framework & relevant forms
Article 132 of Law no. 4001/2011 as in force (based on Article 69(7) of Law 4602/2019)
More
Article 132 of Law no. 4001/2011 as in force (based on Article 69(7) of Law 4602/2019)
More
Protection/DIE/89003/443 (Government Gazette B 5674/17.12.2018)
More
Procedure for the connection of an auxiliary power station
More
Application form for the connection of an auxiliary power station
More
Additional Agreement for an auxiliary power generation
More